From the 20th May 2021, the Department of Planning, Industry and Environment gave the Collector Wind Farm Project Approval MP10_0156 – Collector Wind Farm: Condition A8D: Commencement of Operations. This means that RATCH-Australia has met all of the requirements for the management plans under conditions E19 and E20; and that the Pre-operations Compliance Report is now complete.

The Collector Wind Farm has now completed handing over the project to the operations and maintenance team. Vestas will be on site to mange the operations and RATCH-Australia will be managing the compliance and the asset management of the Collector Wind Farm. 

The Collector Wind Farm is not open to the public but can be viewed from the Hume Highway. If you do have any questions about the wind farm please contact us via 1800 280 013 or via email at enquiries@ratchaustralia.com

Compliance

Operations

The wind farm will be managed in accordance with the Operational Environmental Management Plan, which was approved by the Department of Planning and Environment (DPE). The plan details key maintenance activities and outlines procedures for monitoring noise, impacts on flora and fauna and minimising fire risk.

– Operational Environmental Management Plan

– Environmental Audit Report 2023

The Operation Noise Management Plan was also approved by the Department of Planning and Environment (DPE). The plan’s overall objective is to define how the owners and operators of the Collector Wind Farm will meet its commitments and obligations under the Project Approval to achieve, demonstrate and maintain compliance with the operational noise criteria specified in the Project Approval. Noise monitoring commenced mid June 2021 and the first Collector Wind Farm Post-Construction Noise Assessment was submitted to the Department on the 25th February 2022. The report was accepted by the Department on 1 March 2022. 

– Operation Noise Management Plan 

– Post-Construction Noise Assessment 2023

One of our main priorities is protecting the local flora and fauna around the Collector Wind Farm. In order to protect the bird and bat population in the area to the best of our abilities we have developed a Bird and Bat Adataptive Management Plan (BBAMP). This approach has been approved by the DPIE.

– Bird and Bat Adataptive Management Plan (BBAMP)

The Pollution Incident Response Management Plan  informs the Environmental Protection Agency (EPA) about what controls we have in place to prevent pollution incidents on the Collector Wind Farm site. If you see any pollution on the wind farm site please call us immediately on 1800 280 013 or email enquiries@ratchaustralia.com

– Pollution Incident Response Management Plan 2023

Bushfire risk management is governed and provisioned by associated legislation, regulation and guidelines as well as the committed mitigation measures and relevant State conditions of approval. The Bushfire Management Plan is reviewed annually and updated. It describes how bushfire risk is managed throughout the operations and management of the Collector Wind Farm.  

– Bushfire Management Plan 2023

The wind farm will be decommissioned in accordance with the Collector Wind Farm – Decommissioning and Rehabilitation Plan, which was approved by the Department of Planning, Housing and Infrastructure (DPHI).