Collector Wind Farm

Construction

Major construction activities commenced in May 2019 and were completed in October 2020. 

The first task was to upgrade the access road to the site, Lerida Road South, which was completed November 2019. Construction of the substation for the project started in September 2019. Work on the turbine foundations began in November 2019, prior to the wind turbines components arriving. Components of the turbines began arriving on site in March 2020, with the last delivered in September 2020.

Each of the wind farm’s 54 turbines comprise three tower sections, three blades, a hub to connect the blades to the tower and a nacelle, which houses the generator. 

In April 2020 the wind turbines started to be erected and the wind farm generated its first clean power in November 2020. Commissioning of the wind farm began in February 2021. Commercial operations commenced in June 2021.

The main challenge for the build was the access to the site as the original road was only used by local farmers and needed a lot of upgrading. The other main challenge for the construction was that it was conducted throughout the pandemic. This meant that there were supply chain issues and the safety of the workforce had to be managed closely.

Vestas Australian Wind Technology managed all construction works, with support from major subcontractors: Symal, civil subcontractors, RJE electrical subcontractor and UGL assisted Transgrid with the electrical and civil work on the sub station.

There are a number of conditions in the development approval that needed to be finalised before construction could start on site.  Some required additional review and approval from the NSW Department of Planning, Industry & Environment.

These conditions are detailed here, with the relevant documentation as well as additional project documents, such as audit reports, management plans and licences, available for view and download below.

Collector Wind Farm

Construction Timeline

May 2019

CONSTRUCTION COMMENCED

July 2019

Site access

September 2019

Construction of substation commences

November 2019

Lerida Road upgrade complete
Foundation pours commence

March 2020

Wind turbine component deliveries commence
Cranes mobilised

April 2020

Wind turbine erection commences

November

Wind turbine energisation

February 2021

Wind farm commissioning commences

June 2021

COMMERCIAL OPERATION

Collector Wind Farm

Construction Gallery

Collector Wind Farm

Project documents

Condition A5 – Confirmation of wind turbine order (PDF 56KB)

Condition A7 – Decommissioning provisions (PDF 150KB)

Condition A8D – Notification of construction commencement (PDF 150KB)

Condition A8B – Micrositing report (PDF 10MB)

Condition A8C – Final layout plans (PDF 2.2MB)

Condition A8C – Turbine co-ordinates (PDF 132KB)

Condition B6 – Bird and Bat Adaptive Management Plan (PDF 1.6MB)

Condition B12 – Aviation Consultation(PDF 1.4MB)

Condition B13 – Aviation information (PDF 6.5MB)

Condition B18 – Bushfire Risk Management Plan(PDF 900KB)

Condition B26 – Nightlighting consultation(PDF 871KB)

Condition B27 – Design and Landscape Plan(PDF 2MB)

Condition B33 – Crown land consultation(PDF 123KB)

Condition B35 – Mineral resources consultation(PDF 120KB)

Condition C2 – Community Enhancement Program (PDF 798KB)

Condition C4 – Community Information Plan (PDF 449KB)

Condition C5 – Enquiry and complaints handling procedure (PDF 312KB)

Condition C7 – Pre-construction compliance report (PDF 577KB)

Condition C10 – Independent Environmental Audit (PDF 12MB)

Condition C10 – Independent Environmental Audit Recommendation Implementation Timetable (PDF 56KB)

Condition D24 – Construction Environmental Management Plan (PDF 6MB)

Condition D25A – Construction Compound and Ancillary Facilities Management Plan (PDF 660KB)

Condition D25B – Construction Noise and Vibration Management Plan (PDF 620KB)

Condition D25C – Construction Traffic and Access Management Plan (PDF 13MB)

Condition D25D – Construction Soil and Water Quality Management Plan (PDF 10MB)

Condition D25E – Cultural Heritage Management Plan (PDF 1.3MB)

Condition E2 – Television and Radio interference (PDF 6MB)

Condition F2 – Decommissioning Plan (PDF 1MB)

Environment Protection Licence (PDF 4.4MB)

Pollution Incident Response Management Plan (PDF 1MB)