YANDIN WIND FARM

Construction

Site works on Yandin commenced in August 2019, with more than 50,000 tonnes of turbines and machinery estimated to have been transported to site during construction.

The project required close to 1 million hours of labour, generating around 150 local jobs over the course of the build.

The turbines are among the biggest ever installed in Australia. At their highest point, the tip blades reach 180m into the air, and the rotor diameter is 150m.

YANDIN WIND FARM

Construction Timeline

July 2019

FINANCE CLOSE

July 2019

Development Approval

August 2019

Start Construction

October 2019

RAC acquisition 70% of Yandin Wind Farm

July 2020

First Generation from the Project

May 2021

Full Commercial Operations